Question: While constructing a new office space, the sponsor has requested the project manager complete the project sooner. While analyzing the work, the project manager has
While constructing a new office space, the sponsor has requested the project manager complete the project sooner. While analyzing the work, the project manager has notice that some of the work can start before the predecessor work is done. What can the project manager do in this scenario to complete the project sooner