Question: While developing an Integrated CostlSchedule system, cost and Schedule variance is computed by Schedule variance (EV-PV) and the cost variance (EV-AC) schedule variance (PV-EV) and
While developing an Integrated CostlSchedule system, cost and Schedule variance is computed by
Schedule variance (EV-PV) and the cost variance (EV-AC)
schedule variance (PV-EV) and the cost variance (AC-EV)
schedule variance (EV-PV)and the cost variance (AC-EV)
Schedule variance (PV-AC) and the cost variance (EV-PV)
none of the above