Question: While identifying stakeholders, you plan to group the stakeholders based on their level of authority and their active involvement in the project. You can do

While identifying stakeholders, you plan to group the stakeholders based on their level of authority and their active involvement in the project. You can do this by using:
Question 14 options:
Power / interest grid,
Power / influence grid
Influence / impact grid
Salience model