Question: while observing an employee at a task the average time to complete the task was 1 3 . 0 the employee was given a performave

while observing an employee at a task the average time to complete the task was 13.0 the employee was given a performave rating 90 while the company grants a 20 allowance for pdf allowences what would be the notmal time and standard time