Question: While _________ the project, the project manager should evaluate the accuracy of the business case and the stakeholder engagement to create a lessons learned register.
While _________ the project, the project manager should evaluate the accuracy of the business case and the stakeholder engagement to create a lessons learned register.
| initiating | ||
| closing | ||
| planning | ||
| executing |