Question: While working on a game design project, the project sponsor has asked the project manager that to ensure that his estimates are very precise. What
While working on a game design project, the project sponsor has asked the project manager that to ensure that his estimates are very precise. What estimating technique should the project manager use? a Top down estimate b Bottom-up estimating c Three-point estimating d Analogous estimating