Question: While working on a project, the sponsor has made it clear that he does not want any of the team members to be overworked. This
While working on a project, the sponsor has made it clear that he does not want any of the team members to be overworked. This means that no team member would be allowed to work overtime. The sponsor is okay if the project is delayed due to this. What technique can the project manager best Implement to ensure that no team member is overworked