Question: Who should receive the monthly projA project manager is evaluating a vendor s work performance. Which one is NOT a benefit of gathering work performance
Who should receive the monthly projA project manager is evaluating a vendor s work performance. Which one is NOT a benefit of gathering work performance data?
It helps with improved vendor communications.
It supports competitive pricing.
It encourages effective risk management.
It assists when there is a dispute with the vendor.ect status reports?