Question: Why do many people inflate their estimates? Does adding safety, in terms of an inflated estimate, to each task or activity ensure that the project
Why do many people inflate their estimates? Does adding safety, in terms of an inflated estimate, to each task or activity ensure that the project will be completed as scheduled? Why or why not? How does Critical Chain Project Management overcome the practice of inflated estimates through the use of buffers?
Step by Step Solution
There are 3 Steps involved in it
Many people may inflate their estimates due to a variety of reasons including wanting to appear comp... View full answer