Question: Why is it critical to develop a time - phased baseline? Because other systems do not measure how much work is accomplished for the money
Why is it critical to develop a timephased baseline?
Because other systems do not measure how much work is accomplished for the money spent! Hence, without timephasing cost to match your project schedule, it is impossible to have reliable information for control purposes.