Question: Why is it critical to develop a time - phased baseline? Because other systems do not measure how much work is accomplished for the money

Why is it critical to develop a time-phased baseline?
Because other systems do not measure how much work is accomplished for the money spent! Hence, without time-phasing cost to match your project schedule, it is impossible to have reliable information for control purposes.