Question: Why is it necessary to consider the learning curve associated with tasks in a project? A. to improve cost estimates B. to improve project team

Why is it necessary to consider the learning curve associated with tasks in a project?

A.

to improve cost estimates

B.

to improve project team morale

C.

because it always takes less time to do a task after someone has done it a few times

D.

collective bargaining contracts require it

E.

All of the above

  1. A(n) __________________ shows the set of all tasks in a project arranged by task level.

    A.

    Linear Responsibility Chart

    B.

    Work Breakdown Structure

    C.

    Gantt chart

    D.

    Design Structure Matrix

    E.

    Aggregate Project Portfolio

What is the first task of a newly appointed project manager?

A.

to negotiate the projects budget

B.

to negotiate with functional managers for key resources

C.

to develop a work breakdown structure for the project

D.

to review the project objectives with senior management

E.

to develop a project plan for the project

Which of the following is used to show linkages between people and tasks?

A.

the Work Breakdown Structure

B.

the RACI Matrix

C.

the Project Master Plan

D.

the Project Resource Diagram

E.

the Concurrent Engineering Chart

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image