Question: Why is it necessary to have a time - phased budget baseline? Multiple Choice It reduces schedule slippage when scheduling multiproject resources. It is not

Why is it necessary to have a time-phased budget baseline?
Multiple Choice
It reduces schedule slippage when scheduling multiproject resources.
It is not necessary to have a time-phased budget baseline.
It shows how much work was accomplished for the money spent.
It reduces fluctuations in cash flow during the project.
It allows proper resource allocation.