Question: Why is it that sometimes adding more human resources to a project that is already late causes that project to become even further delayed? Under

  • Why is it that sometimes adding more human resources to a project that is already late causes that project to become even further delayed?
  • Under what circumstances is itappropriate to add more human resources to a project?

Step by Step Solution

3.38 Rating (151 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Adding more human resources to a project that is already late can sometimes result in further delays due to a phenomenon known as the mythical manmonth effect This concept coined by Fred Brooks in his ... View full answer