Question: Why is it that sometimes adding more human resources to a project that is already late causes that project to become even further delayed? Under
- Why is it that sometimes adding more human resources to a project that is already late causes that project to become even further delayed?
- Under what circumstances is itappropriate to add more human resources to a project?
Step by Step Solution
3.38 Rating (151 Votes )
There are 3 Steps involved in it
Adding more human resources to a project that is already late can sometimes result in further delays due to a phenomenon known as the mythical manmonth effect This concept coined by Fred Brooks in his ... View full answer