Question: Why is the answer 9? Please explian and show work An assembly line with 9 tasks is to be balanced. The longest task is 9

Why is the answer 9? Please explian and show work
Why is the answer 9? Please explian and show work
An assembly line with 9 tasks is to be balanced. The longest task is 9 minutes, the shortest task is 3 minutes, and the sum of the task times is 56 minutes. The line will operate for 7 hours per day, 2 shifts per day, 6 days per week. What is the minimum possible cycle time for this line? Answer: 9 Check

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock