Question: Why is the project management plan considered an input to the risk management process? Group of answer choices It includes a detailed budget for risk
Why is the project management plan considered an input to the risk management process? Group of answer choices It includes a detailed budget for risk management activities. It lists all potential project risks. It provides a baseline and the current state of the project for assessing risks. It defines the project's objectives and outcomes