Question: Why is the three-point time estimating technique a good way to determine a confidence rating for your time estimates? O It ensures you have considered

Why is the three-point time estimating technique a good way to determine a confidence rating for your time estimates? O It ensures you have considered the best-case and worst-case conditions for a task. O It is the time estimating technique that involves input from the most people. O It is a commonly used technique that everyone is familiar with. O It removes all uncertainty from your estimate