Question: 1 . Question 1 You are managing a construction project and must pour the foundation before you can move on to the building phase of

1.
Question 1
You are managing a construction project and must pour the foundation before you can move on to the building phase of your project. You have ordered the required materials, selected the best team members to execute the pouring, and scheduled a day to when the foundation will be poured. Which of the following represents a milestone in your project plan?
1 point
Completing the foundation
Selecting team members
Receiving required materials
Scheduling a day to pour the foundation
2.
Question 2
One of the tasks in your project involves setting up the stage for a talent show. Before the team can do this, you need estimates from an audiovisual contractor, and the construction crew needs to build the stage backdrop. What term refers to these preliminary needs?
1 point
Milestones
Vendors
Project scope
Task dependencies
3.
Question 3
Which of the following terms refer to knowledge of a specific industry, such as industry terms, techniques, and processes?
1 point
Intellectual property
Domain knowledge
Competitive intelligence
Enterprise learning
4.
Question 4
To identify project tasks for your project plan, you review project documentation and research your project online. You have connected with members of your project team and other experts in your organization to examine your list of tasks. You decide you need additional details about a key deliverable. Who should you speak to in order to receive the missing information?
1 point
Your companys Chief Operating Officer
Your most senior stakeholder
One of your high-influence stakeholders
Your companys most senior project manager
5.
Question 5
Determining the proper task order will help you assign start and end dates for each task. When determining task priorities, what should you consider first?
1 point
The number of team members available for the project
The target date for completing the project
Which team members will address each task
The basic order of operations
6.
Question 6
When identifying a project milestone, which of the following describes what you are seeking?
1 point
The first task in your project schedule
The last task in your project plan
Tasks that signal the completion of a project phase
Tasks that signal customer payments are due
7.
Question 7
What term refers to a time estimate that only takes into account the actual time it takes to complete a task?
1 point
Taskflow duration estimate
Total duration estimate
Milestone estimate
Effort estimate
8.
Question 8
Which of the measures involved in three-point time estimations is based on how long the task usually takes under normal circumstances, with only slight adjustments to the best-case scenario?
1 point
Optimistic time estimates
Most likely time estimates
Planning time estimates
Pessimistic time estimates
9.
Question 9
Why is the three-point time estimating technique a good way to determine a confidence rating for your time estimates?
1 point
It ensures you have considered the best-case and worst-case conditions for a task.
It is the time estimating technique that involves input from the most people.
It removes all uncertainty from your estimate.
It is a commonly used technique that everyone is familiar with.
10.
Question 10
When you ask questions of your team members without showing empathy, you can leave them feeling too closely observed, controlled, or continuously reminded of the work they have been assigned. What is the term that expresses this negative impact your team members feel in this case?
1 point
Harassment
Arguing
Justifying
Micromanaging

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!