Question: Window Cleaning Schedule Building A Can't happen first Building B Must happen before Building D Building C Must include the 1 2 th in the

Window Cleaning Schedule
Building A
Can't happen first
Building B
Must happen before Building D
Building C
Must include the 12th in the schedule
Building D
Must happen before Building A
Question
Four buildings are scheduled for window cleaning, one at a time. Each building takes 4 days. The cleaners do not start a new job on Mondays or work weekends. On which date should the work on Building A begin, to complete all 4 buildings as early as possible?
Calendar
\table[[SUN,MON,TUE,WED,THU,FRI,SAT],[7,1,2,3,4,5,6],[14,8,9,10,11,12,13],[21,15,16,17,18,19,20],[28,29,23,24,25,26,27]]
Window Cleaning Schedule Building A Can't happen

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!