Question: Windsor Co. (Windsor) has a contract to build a building for $100,000, with an estimated completion time of three years. A reliable cost estimate for

Windsor Co. (Windsor) has a contract to build a building for $100,000, with an estimated completion time of three years. A reliable cost estimate for the project would be $60,000. In the first year of the project, Windsor incurred costs totaling $24,000. Under the completed contract method, in the first year Windsor will report a profit of:

$16,000. $40,000. $0. $36,000.