Question: With a blank, new project open in MS Project, click File tab>>Options>>Schedule. In the Scheduling options for this project section, change the dropdown to All
With a blank, new project open in MS Project, click File tab>>Options>>Schedule. In the "Scheduling options for this project" section, change the dropdown to "All New Projects." Then change the "New tasks created" option to __________ and click OK. This will cause the program to calculate the projects' running schedule based on task start and finish dates.
a. Manually Scheduled
b. Auto Scheduled
c. Timeline View
d. View Shortcuts