Question: With a turnkey construction contract, the contractor guarantees the SPV: A. The completion date and performance of the plant, but not the cost of the
-
With a turnkey construction contract, the contractor guarantees the SPV:
A. The completion date and performance of the plant, but not the cost of the works.
B. The performance and the cost of the plant, but not the completion date.
C. The completion date, plant performance and the cost of the works.