Question: With a turnkey construction contract, the contractor guarantees the SPV: a) The completion date and performance of the plant, but not the cost of the
a) The completion date and performance of the plant, but not the cost of the works.
b) The performance and the cost of the plant, but not the completion date.
c) The completion date, plant performance and the cost of the works.
Step by Step Solution
3.39 Rating (174 Votes )
There are 3 Steps involved in it
C The turnkey agreement is a construction contract ... View full answer