Question: with explantaion 5. A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along

with explantaion 5. A project being analyzed by
with explantaion
5. A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, the probability that the project will take 224 days or more to complete is A) near zero B) 0.0126 C) 0.1587 D) 0.8413 E) 2.14