Question: With PERT scheduling, there are three duration estimates to each activity, an optimistic, pessimistic and a most likely duration and the duration used for calculating
With PERT scheduling, there are three duration estimates to each activity, an optimistic, pessimistic and a most likely duration and the duration used for calculating the start and finish dates is the mean of those three durations. (O + L + P) divided by 3.
True or False