Question: With using the network diagram below, find out; a ) Early and late stare finish times ( 5 p ) . b ) Total completion
With using the network diagram below, find out; a Early and late stare finish times p b Total completion time of the diagram p c Total float values of the activities p d Highlight the critical path on the diagram p
Locate an activity with independent float, if available. p