Question: Activity A Duration (week) Predecessor B 11 12 C 5 3 A E 11 B,C F 9 B,C G 5 B,C H 3 I

Activity A Duration (week) Predecessor B 11 12 C 5 3 A

Activity A Duration (week) Predecessor B 11 12 C 5 3 A E 11 B,C F 9 B,C G 5 B,C H 3 I 7 G,H J 3 D,E Given the above activates solve the following: 1. Constructing the above network diagram using Gantt Chart Techniques and CPM. 2. Fine out the total completion time of the project. 3. Calculate the critical and non-critical path of both network diagram Gantt chart and CPM diagram. 4. Find out the float of all the activates and explain meaning of float A,B,and C 5. What is PERT network diagram, and what makes it differ from CPM. 6. Attached example of PERT and explain the result.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Answer This Questions Step by Step Data Correction Clarification It appear the providede table has some formatting issues in the transcription Based on the visual structure heres the corrected data we... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!