Question: Within the Work Breakdown Structure below, how much of the work included in deliverable 1.1 is explained by work-packages within activities 1.1.1&1.1.2? begin{tabular}{r|r|r|} & 1.0

Within the Work Breakdown Structure below, how much of the work included in deliverable 1.1 is explained by work-packages within activities 1.1.1&1.1.2? \begin{tabular}{r|r|r|} & 1.0 & \\ \hline 1.1 & 1.2 & 1.3 \\ \hline & & \\ \hline \end{tabular} 25 100 0 50