Question: woman Denotes critical path link - Denotes zero link lag value -Denotes positive link lag value (shown) Activity B E H ES Dur 3 EF

woman Denotes critical path link - Denotes zero link lag value -Denotes positive link lag value (shown) Activity B E H ES Dur 3 EF 12 16 A C F J L 16 5 16 21 28 D G K 3 2 3 8 15 16 3 19 Normal Crashed Normal Activity Duration Duration Cost Crash Cost # : CN = CC A 1 1 $800 $80 B 4 $1,000 $1,600 C 6 4 $300 $500 D $400 $800 $100 $200 $500 $80 $200 $1,400 I Q $350 $60 w $700 $850 $500 $1,000 $450 $80 Based on the network diagram and the given data table above, provide step-by-step crashing. Three completed table need to be solved. For each crashing cycle, provide updated network diagram. Your answer should be shown in a similar fashion as the example from Week 10
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
