Question: Work breakdown structure for a project is given below. What is the critical path? Task Time taken by task Predecessors A 5 B 3 A

Work breakdown structure for a project is given below. What is the critical path? Task Time taken by task Predecessors

A 5 B 3 A C 4 A D 6 B E 8 B F 7 C G 5 D, E H 6 F I 4 C, F J 2 G, H, I

Group of answer choices

A-C-F-H-J

A-B-E-G-J

A-C-F-I-J

A-B-D-G-J