Question: Work breakdown structure for a project is given below. What is the critical path? Task Time taken by task Predecessors A 3 B 6 A
Work breakdown structure for a project is given below. What is the critical path?
| Task | Time taken by task | Predecessors |
| A | 3 | |
| B | 6 | A |
| C | 3 | A |
| D | 2 | B |
| E | 8 | B |
| F | 5 | B, C |
| G | 6 | D, E |
| H | 2 | F |
| I | 1 | F |
| J | 7 | G, H, I |
1. A-C-F-I-J
2. A-C-F-H-J
3. A-B-E-G-J
4. A-B-F-I-J