Question: Work breakdown structure of some ATM software is given below in list form: TASK Duration Predecessor Requirement Analysis 1.1. Describe system architecture 20 days 1.2.
Work breakdown structure of some ATM software is given below in list form:
TASK Duration Predecessor
|
Using the above WBS,
-Create the Gantt chart for the project.
-How long will it take to complete this project? You may ignore inconsistencies in estimations.
-Name two of the critical tasks.
-Assuming that every person in the team is multi-functional, roughly how many people are required?
Please use Microsoft Excel