Question: Work Design & Measurement i Help Problem 7 - 1 ( Algo ) An analyst has timed a metal - cutting operation for 5 0

Work Design & Measurement i
Help
Problem 7-1(Algo)
An analyst has timed a metal-cutting operation for 50 cycles. The average time per cycle was 8.8 minutes, and the standard deviation was 1.08 minutes for a worker with a performance rating of 108 percent. Assume an allowance of 8 percent of job time. Find the standard time for this operation. (Do not round intermediate calculations. Round your final answer to 2 decimal places.)
Standard time
minutes
Prev
1 of 7
Next
 Work Design & Measurement i Help Problem 7-1(Algo) An analyst has

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!