Question: Work on a project requiring 32 work days (no weekend work) is scheduled to begin on the (morning of) March 2 (March 2 is Day
Work on a project requiring 32 work days (no weekend work) is scheduled to begin on the (morning of) March 2 (March 2 is Day 1). The results of the project will be made available to the customer on the first week day (Monday through Friday, normal business day) following the last day the project is worked on. On what date (month and day) does the customer have first use of the project results? Ignore any holidays that may be in the interval (ANSWER FORMAT: MM/DD ONLY!). (5 points)