Question: Work on a project requiring 32 work days (no weekend work) is scheduled to begin on the (morning of) March 2 (March 2 is Day

Work on a project requiring 32 work days (no weekend work) is scheduled to begin on the (morning of) March 2 (March 2 is Day 1). The results of the project will be made available to the customer on the first week day (Monday through Friday, normal business day) following the last day the project is worked on. On what date (month and day) does the customer have first use of the project results? Ignore any holidays that may be in the interval (ANSWER FORMAT: MM/DD ONLY!). (5 points)

Work on a project requiring 32 work days (no

12. Work on a project requiring 32 work days (no weekend work) is scheduled to begin on the morning of) March 2 (March 2 is Day 1). The results of the project will be made available to the customer on the first week day (Monday through Friday, normal business day) following the last day the project is worked on. On what date (month and day) does the customer have first use of the project results? Ignore any holidays that may be in the interval (ANSWER FORMAT: MMDD ONLY!). (5 points) January Su M Tu W Th F Sa 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 February Su M Tu W T F Sa 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 March Su M Tu W Th F Sa 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 April Su M Tu W Th F Sa 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 May Su M Tu W Th F Sa 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 June Su M Tu W T F Sa 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 B E H F G 20 4 13. Durations of activities is determined by the number of staff assigned. Activity A D E F G Predecessors A A B CD E Person Days 2 12 24 10 28 15 12 Duration Staff Assigned 1 3 3 2 4 5 12 ES EF LS LF a. How many activities are on the critical path if the LF is set to the EF + 2? (16 points) b. What is the critical path duration? (3 points) c. Which Activity has the highest slack? (3 points) d. What minimum staff assignment (number of staff) might be assigned to the highest slack Activity to level staff numbers without changing the EF? Note only integer values can be assigned. (3 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!