Question: worksheet enter calculations to complete the table. In cell ( E 4 , use the WORKDAY function to calculate the end date for the Demolition

worksheet enter calculations to complete the table.
In cell (E4, use the WORKDAY function to calculate the end date for the Demolition task.
Reference the "Holiday Schedule" in your function.
Copy and paste down to E10 to calculate the end date for the other tasks.
Note the calculation will show dates for 1900 until you complete the next calculation.
In cell D5, reference the date you calculated in cell E4 as the start date for the next remodel task.
Copy and paste down to cell (D10) to calculate the start dates for the remaining tasks.
In cell F4, use the NETWORKDAYS function to calculate the number of days each task will take to complete.
Reference the "Holiday Schedule" in your function.
Copy and paste the function down to cell F10 to calculate the number of days for the
 worksheet enter calculations to complete the table. In cell (E4, use

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!