Question: Write a network diagram based on this table Activity Predecessor Optimistic Most Pessimistic te (i) (ii) | 2 3 4 5 I 6 I 7

Write a network diagram based on this tableWrite a network diagram based on this table

Activity Predecessor Optimistic Most Pessimistic te (i) (ii) | 2 3 4 5 I 6 I 7 5 8 6, 7 9 2 10 3 || 4 12 8 13 || 14 9, 12 10, 13, 14 45 15 (a) Likely (b) (a+4m+b)/6 (b-a) (m) (iii) (iv) (v) (vi) (vii) 20 18 22 19 0.111 30 30 30 30 0 60 72 90 73 25 18 27 30 26 4 17 29 47 30 25 4 7 10 7 I 12 15 18 15 | 6 12 24 13 9 18 27 30 ? ? 20 35 50 ? ? 40 55 100 ? ? || 20 29 9 14 23 26 4 13 16 I 0 0 0 19 0 2260 Variance Critical? (viii) 16