Question: Use the values in the table to calculate activity durations for the project. Use PERT and add the values to the template provided. Once you
Use the values in the table to calculate activity durations for the project. Use PERT and add the values to the template provided. Once you have calculated the durations, draw your network diagram (take a picture and upload it). Perform a forward pass and a backwards pass. Identify the critical path (write it in the answer template).
| Activity | Predecessor | Optimistic | Likely | Pessimistic |
| A | -- | 4 | 6 | 10 |
| B | A | 2 | 5 | 8 |
| C | A | 6 | 7 | 9 |
| D | B | 3 | 9 | 20 |
| E | C | 7 | 9 | 11 |
| F | D,E | 7 | 11 | 19 |