Question: Calculate NPV Method. Use a 10% discount rate. Please show how you received the calculations Year Project A Project B 2014 ($3,000,000) ($3,000,000) 2015 $0
Calculate NPV Method. Use a 10% discount rate. Please show how you received the calculations
Year | Project A | Project B |
2014 | ($3,000,000) | ($3,000,000) |
2015 | $0 | $975,000 |
2016 | $600,000 | $975,000 |
2017 | $900,000 | $975,000 |
2018 | $2,700,000 | $975,000 |
Step by Step Solution
3.38 Rating (148 Votes )
There are 3 Steps involved in it
Present value of inflowscash inflowPresent value of discounting factorratetime p... View full answer
Get step-by-step solutions from verified subject matter experts