Question: X=48 Week 1 2 3 4 5 6 7 8 Gross Requirements 35 20 5+X 25 5+X 25 5+X 25 Orders 5 6 4 Projected
X=48
| Week |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Gross Requirements |
| 35 | 20 | 5+X | 25 | 5+X | 25 | 5+X | 25 |
| Orders |
| 5 | 6 | 4 |
|
|
|
|
|
| Projected Available Balance | X |
|
|
|
|
|
|
|
|
| Available-to-promise |
|
|
|
|
|
|
|
|
|
| MPS |
|
|
|
|
|
|
|
|
|
MPS Lot Size = X
The following events occurred during week 1:
- Actual demand during week 1 was only 32 units
- The forecast for week 9 is 10 + X
- An order for 15 in week 2 was accepted.
- An order for 10 in week 4 was accepted.
- An order for 5 in week 3 was accepted.
- The MPS in week 1 was produced as planned
b. Update the record below after rolling through time.
| Week |
| 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
| Gross Requirements |
| 20 | 5+X | 25 | 5+X | 25 | 5+X | 25 | 10+X |
| Scheduled Receipts |
|
| 50 |
|
|
|
|
|
|
| Projected Available Balance |
|
|
|
|
|
|
|
|
|
| Planned Order Release |
|
|
|
|
|
|
|
|
|
MPS Lot Size = X
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts