Question: XAMPLE 3 . 3 Manufacturing Lead Time A certain part is produced in batch sizes of 1 0 0 units. The batches must be routed
XAMPLE Manufacturing Lead Time
A certain part is produced in batch sizes of units. The batches must be routed through five operations to complete the processing of the parts. Average setup time is atch, and average operation time is Average nonoperation time is for each operation. Determine the manufacturing lead time to complete one batch, assuming the plant runs day, dayswk
Step by Step Solution