Question: XYZ project has a total budget for $ 1 , 2 0 0 , 0 0 0 . The project is currently in its 4

XYZ project has a total budget for $1,200,000. The project is currently in its 4 th month of its 12-month timeline but has accomplished only 25% of its activities and has spent 41% of Its financial resources according to the latest financial report. What is the planned value?
$300,000
$400,000
$492,000
$1,200,000