Question: You are a manager for a large machine installation project at your facility. It is broken down into the following tasks with estimated task times

You are a manager for a large machine installation project at your facility. It is broken down into the following tasks with estimated task times and predecessor relationship. Also given are estimated costs.
Estimated Task Time
Task ID
Task Name
Predecessor
Cost / Day
Total Cost
8
A
Site Evaluation
150
1200
10
B
Initial Design
200
2000
12
C
Design Approval
A,B
100
1200
5
D
Order Materials
C
300
1500
12
E
Initiate Foundation Work
C
80
960
14
F
Design and Install Electrical
D
60
840
8
G
Design and Install Plumbing
D
200
1600
6
H
Design and Install HVAC
F,G
300
1800
12
I
Machine Installation
E,F
120
1440
4
J
Task Name
I, H
150
600

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!