Question: You are a planner and you are responsible for developing a time schedule for a project consists of 100 steel frames. The main activities are

You are a planner and you are responsible for developing a time schedule for a project consists of 100 steel frames. The main activities are shown in Table 6. Activity Duration Constraints Foundation 40 Starts before framing by 10 days Framing 50 Finishes after finishing the foundation by 12 days Starts after starting framing by 8 days Cladding 36 Finishes after finishing the framing by 9 days Starts after starting cladding by 7 days Decking Finishes after finishing cladding by 10 days 30 Table 6 A. Draw the Activity on Node (AON) showing all calculations. B. Draw the Activity on Node (AOA) showing all calculations