Question: You are a Program Manager at Hearthstone Custom Cabinets and your client has asked you to complete the following project in eight days. Task Predecessors
You are a
Program Manager
at
Hearthstone Custom Cabinets
and your client has asked you to complete the following project in eight days.
| Task | Predecessors | Normal Time (days) | Crash Time (days) | Normal Cost ($) | Crash Cost ($) |
| A | - | 4 | 2 | 300 | 500 |
| B | - | 3 | 2 | 400 | 650 |
| C | A,B | 2 | 1 | 800 | 1000 |
| D | B | 3 | 1 | 500 | 1100 |
| E | D | 3 | 2 | 350 | 600 |
| F | C | 4 | 3 | 600 | 900 |
| G | B | 7 | 6 | 600 | 700 |
Hearthstone Custom Cabinets
Duration:Based on Normal Task Times what is the current estimated duration of the project?
enter your response here days
Budget:Based on Normal Task Times and Normal Costs, what is the current estimated project budget?
$enter your response here
(please round to the nearest whole dollar)
Crash Cost:What is the additional cost to "crash" the project to achieve a duration of eight days?
$enter your response here
(please round to the nearest whole dollar)