Question: You are a project manager for a motion picture studio. You want to predict the project's total cost. If you have a BAC (budget at
You are a project manager for a motion picture studio. You want to predict the project's total cost. If you have a BAC (budget at completion) of $250,000 and the CPI (cost performance index) is .85, what is the EAC (estimate at completion) for the project?This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A $340,000 option B $294,117 option C $250,000 option D $0.85