Question: You are a project manager for a project that is 80% complete. Your boss authorizes a new project and reassigns all of your team to

You are a project manager for a project that is
You are a project manager for a project that is 80% complete. Your boss authorizes a new project and reassigns all of your team to the new project.Which of the following addresses the purpose of Validate Scope in this case? a) Validate scope documents the level and degree of completion. b) Validate scope documents the correctness of work according to stakeholders' expectations. c) Validate scope determines whether the project results comply with quality standards. d) Validate scope determines the correctness and completion of all the work