Question: You are a project manager for a small construction project. Your project was budgeted for $ 7 2 , 0 0 0 over a six
You are a project manager for a small construction project. Your project was budgeted for $ over a sixweek period. As of today, you've spent $ of your budget to complete work that you originally expected to cost $ According to your timeline, you should have spent $ by this point. Based on these circumstances, your project could be BEST described as:
Not enough information provided to make a decision
Behind schedule.
Ahead of schedule.
on schedule