Question: You are a project manager for the TTY project. You are in the process of classifying stakeholders' engagement to document at what levels of engagement
You are a project manager for the TTY project. You are in the process of classifying stakeholders' engagement to document at what levels of engagement your stakeholders are. You observe that one of the stakeholders is aware of the project and its potential impacts, and is actively engaged in ensuring that the project is a success. In which of the following engagement levels will you classify that stakeholder? This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A Resistant option B Neutral option C Leading option D Supportive