Question: You are a project manager in a weak matrix. You have recently completed the project schedule. You must now get the project schedule approved. Which
You are a project manager in a weak matrix. You have recently completed the project schedule. You must now get the project schedule approved. Which one of the following stakeholders will need to approve the project schedule?
A Functional managers.
B Project champion.
C Project team members.
D No one. The project manager has autonomy on the project in this structure.