Question: You are a project manager on a large project using the earned value reporting system to manage your project. At this point in time the
You are a project manager on a large project using the earned value reporting system to manage your project. At this point in time the EV is $24000, the BAC is $97000, the PV is $29000, and the AC is $45000. What is the percent complete?